The West African Gas Pipeline Company (WAPCo) has successfully completed critical maintenance on its regional pipeline system, restoring gas transportation services across Ghana, Togo, and Benin ahead of schedule.
The West African Gas Pipeline Company Limited (WAPCo) announced last week that 70% of its ongoing maintenance work had been completed, moving the company closer to resuming gas supply to Tema.
The maintenance project was initially scheduled for February 3, 2025, and expected to be fully completed by March 2, 2025.
The four-week maintenance project involved offshore pipeline cleaning and inspection, subsea valve replacements, and other essential works across multiple locations in Ghana, Togo, Benin, and Nigeria.