1D1F: Brick factory in Tano North District takes shape

1D1F: Brick factory in Tano North District takes shape

A factory under construction in the Tano North District in the newly created Ahafo Region intended to produce bricks for housing and related projects is near completion.

The factory which is under the Government’s flagship project, One-District-One-Factory (1D1F), is about 85% complete, with the remaining 15% expected to be completed in two weeks time.

The National Coordinator of the 1D1F project, Mrs. Gifty Ohene-Konadu, toured the project site to have first-hand information about the level of progress of the brick factory.

Owners of the brick factory, Rhovanni Royal Limited, told her they are on track to commence operations in the second quarter of the year.

“The only thing left is the roofing works which have been awarded to Metallex. All the machines and equipment needed to operate have also been procured and will soon take delivery of them”, CEO of Rhovanni Royal Limited, Carl Christian Lokko, said.

Tanoso is notably known for its abundant clay, a raw material that the company is banking its hopes on to produce bricks for the housing and construction industry.

The company has so far acquired 37.79 acres of land which it will depend on for the supply of the raw material to feed the factory. It is also in the process of acquiring a further 80 acres of land to augment what it has already acquired.

Mr. Lokko believes that the acquisition of land will sustain the company to be in business for more than thirty (30) years.

“Clay which is the raw material we are going to depend on is in abundance in Tanoso. The 37.79 acres of land we have acquired can keep us in operation for more than thirty years and we’re still in the process of acquiring a further 80 acres of land,” he stated.

Mr. Lokko explained he and his team are prepared to run and sustain the brick business.

The factory, he added, will produce 125 tons of bricks a day when operating at full capacity.

1D1F Ahafo brick factory

However, Mr. Lokko said the company will first operate only one line when it commences production and gradually roll out the remaining three in some few months’ time.

1D1F Ahafo brick factory

The company is expected to generate direct and indirect employment to 1,800 people.

Mrs. Ohene-Konadu commenting on the project said government wants to take its time to ensure that all factories under the 1D1F program have good foundations before they are commissioned.

1D1F Ahafo brick factory

“In constructing a factory, if you don’t do it well, it won’t last. Therefore, you have to get the foundation right and I am happy Rhovanni is laying a good foundation where the equipment will be mounted,” she stated.

1D1F Ahafo brick factory

The project, she noted, is being supported by the EXIM Bank of Ghana.

The 1D1F National Coordinator also toured some project sites in Techiman and Atebubu-Amantin District in the Bono East Region where works are ongoing to inject life into an abandoned puree processing factory.

1D1F Ahafo brick factory

She also toured a starch factory which is going to be managed by Webcon Engineering limited. These companies are expected to address the unemployment situation in those areas.

1D1F Ahafo brick factory

Mr. Wil Aparloo Ofori, CEO of Techiman Processing Complex Limited (TEPCO) told Mrs. Ohene-Konadu how grateful they are to the government for reviving the puree processing factory which has been abandoned for over five years.

1D1F Ahafo brick factory

According to him, once the company is in operation, it could process about four or five tons of raw materials supplied to it.

1D1F Ahafo brick factory

The company, he added, will also give direct employment to about 100 people who will be running two shifts on daily basis with a further 1000 people expected to gain employment in the supply chain.

Mrs. Ohene-Konadu said “TEPCO already has the plants and equipment to be in business so we will not sit down for it to be a white elephant.”

1D1F Ahafo brick factory

According to her the company also has some improved seedlings to boost their raw material base, “they will process tomato, mango and watermelon during the respective seasons of those fruits.”

1D1F Ahafo brick factory

She revealed GCB Bank has approved some funding for TEPCO to start all over again.

1D1F Ahafo brick factory

At Atebubu-Amantin where a 300 tons starch factory is under construction, Mrs. Ohene-Konadu said she was hopeful the project will be completed on the scheduled time for production to commence.